Energize & Backfeeding of Sumsel-8 Mine Mouth Steam Power Plant

Tanjung Lalang, 05 Jun 2023 · Operations

Energize & Backfeeding of Sumsel-8 Mine Mouth Steam Power Plant

Sumsel-8 Mine Mouth Steam Power Plant, known as PLTU Tanjung Lalang, located in Muara Enim South Sumatra Indonesia achieved an important milestone on May 7, 2023 with the first time this power plant received Backfeeding Power from PT PLN (Persero).

PLTU Tanjung Lalang is the largest mine mouth power plant in Indonesia with an installed capacity of 1,320 MW.

Backfeeding process, also known as grid synchronization to guarantee commissioning test of new power plants.

In this case, synchronization and testing become very important to ensure the plant can deliver power safely and reliably, also ready for commercial operation.

PLTU Tanjung Lalang is a major investment in Indonesia's energy infrastructure and is critical in its role in supplying Indonesia's growing demand for electricity.

PLTU Tanjung Lalang is one step closer to full operation after achieving success in obtaining Backfeeding Power, which marks a significant milestone in the construction process.

With the inclusion of electricity from PLTU Tanjung Lalang, it is hoped that it will be able to meet the nation's increasing energy needs, especially in Sumatra.